šÆ What is Master Production Schedule (MPS)?
The Master Production Schedule is a strategic production planning tool that creates a detailed week-by-week
plan for the next 12 weeks. It tells you what to produce, when to produce it, and how much,
while balancing customer demand with your production capacity.
Key Benefits:
- 12-week visibility into production needs
- Balanced capacity utilization (target: 80-90%)
- Timely material ordering through MRP integration
- Accurate delivery date promises to customers
- Reduced firefighting and rush orders
š Understanding Time Fences
The MPS uses 4 time horizons with different rules:
- Frozen (Weeks 1-2): Production is scheduled, materials ordered. Cannot change. Any changes require executive approval and may cause delays/waste.
- Firm (Weeks 3-4): Materials being ordered. Only ±10% changes allowed with manager approval. Larger changes may incur rush fees.
- Planned (Weeks 5-8): Fully adjustable. Best time to make changes. Materials not yet ordered.
- Tentative (Weeks 9-12): Forecast-based, provides long-term visibility. Can be freely adjusted as forecasts improve.
š How to Read the Calendar
The calendar shows each product across 12 weeks:
- Product Rows: Each row represents one product
- Week Columns: 12 columns for weeks 1-12
- Cell Numbers: Planned production quantity for that week
- Cell Border Colors: Indicate time fence (Frozen=Red, Firm=Yellow, Planned=Green, Tentative=Purple)
- Capacity Bar: Shows % utilization (Green=optimal, Yellow=near-max, Red=overload)
- Status Dot: Quick visual of capacity status
Click any week cell to see detailed information about time fence rules for that period.
ā” Generating MPS (4 Steps)
- Gather Demand: System pulls confirmed sales orders and forecasts
- Check Capacity: Verifies production lines can handle the load
- Create Plan: Generates 12-week schedule using selected strategy
- Validate & Freeze: Review and freeze weeks 1-2
Strategies:
- Chase Demand: Match production exactly to demand each week
- Level Loading: Smooth production across all weeks
- Hybrid (Recommended): Chase in frozen/firm, level in planned/tentative
š
Weekly MPS Process
Monday Morning (8:00-8:30 AM):
- Click "Refresh Data" to load current schedule
- Review upcoming week (frozen zone) - confirm it's locked in
- Check weeks 2-4 for any critical changes needed
- Review weeks 5-12, adjust for new orders or forecast changes
- Click "Optimize Schedule" to balance capacity
- Click "Generate MPS" to update with latest demand
- Review MRP dashboard for material requirements
Time Investment: 30 minutes/week vs 4-6 hours with manual planning
šÆ Optimization Strategies
Level Loading: Smooths production to avoid peaks and valleys. Best for reducing overtime and maintaining steady workflow.
When to Optimize:
- Overload weeks (>100% capacity) - red bars in capacity chart
- Underload weeks (<70% capacity) - wasted capacity
- Uneven distribution causing frequent changeovers
- After adding new sales orders
ā ļø Handling Overloads
When a week shows >100% capacity (red bar):
- Move to Earlier Week: Pull production forward if capacity available
- Move to Later Week: Push to future if customer can wait
- Add Overtime Shift: Temporarily increase capacity (costs more)
- Outsource: Use contract manufacturer (if time-sensitive)
- Negotiate Delivery: Work with customer on new date
š Integration with Other Systems
MPS ā MRP: Your MPS automatically feeds the MRP system, which calculates material requirements for each planned production run.
MPS ā Production Floor: Week 1 (frozen) becomes the production floor schedule. Shop floor managers execute against this plan.
Sales Orders ā MPS: Confirmed sales orders automatically populate MPS demand calculations.
MPS ā Feasibility Checker: When sales team enters new orders, feasibility checker uses MPS to promise accurate delivery dates.
š Success Metrics (KPIs)
- Schedule Adherence: Target >95% (actually produce what you planned)
- Capacity Utilization: Target 80-90% (not too high, not too low)
- Forecast Accuracy: Target >85% (how well forecasts match actuals)
- Changeover Time: Track time lost switching between products
ā Common Questions
Q: What if I get an urgent order for a frozen week?
A: Escalate to manager. May require: (1) Overtime shift, (2) Displacing another order, (3) Rush material fees, or (4) Negotiating delivery date.
Q: How often should I update MPS?
A: Weekly minimum. More frequent updates (2-3x/week) recommended for fast-changing environments.
Q: What if capacity is consistently over 100%?
A: Long-term solutions: (1) Add production line/shift, (2) Hire more workers, (3) Invest in faster equipment, (4) Outsource overflow, or (5) Limit sales to capacity.
š” Best Practices
- Never change frozen weeks without executive approval
- Freeze week 1 by Friday prior to start of that week
- Review MPS every Monday morning (30 minutes)
- Run "Optimize Schedule" after major changes
- Keep utilization between 80-90% (not 100%!)
- Coordinate with procurement on material lead times
- Use tentative weeks (9-12) for scenario planning
- Track schedule adherence weekly
- Hold weekly MPS review meeting with key stakeholders
- Document reasons for any changes to frozen/firm weeks
š§ Need Help?
For questions or issues with the MPS system, contact:
Production Planning Team
Email: [email protected]
Phone: (555) 123-4567